BOM vs routing: the bill of materials and the manufacturing routing, with an example
Published November 18, 2026 — what the product is made of and how it is made: the bill of materials, the routing, component allocation to operations, a worked example, the work order that brings them together, the ERP and a time and cost calculator.
In short: the bill of materials (BOM) says what the product is made of: components and quantities. The routing says how it is made: the sequence of operations, the work centre of each and its setup and run times. The work order brings both together: a list of components to pick and a list of operations to perform. So does the product cost: material comes from the BOM, labour and machine time from the routing.
1. What and how: BOM and routing
2. The worked example: the cart's routing
We take the cart from the BOM series. Here is a possible routing, with example times and hourly rates, to be replaced by your shop's:
For a work order of 10 carts: time = setup + 10 × run, i.e. 55, 270, 130, 190 and 50 min, 695 min (11.6 h) in total; cost = time × rate, i.e. 614.6 for the order and 61.5 per cart, in the hourly rate's currency. For 1 cart, the same calculation gives 137 min and 121.1 per cart: the 75 minutes of setup are no longer shared. That is what batch size is all about.
3. Routing time and cost calculator
Paste your routing, one line per operation: operation; work centre; setup (min); run time (min); hourly rate. Enter the order quantity: the calculator gives the time and cost of each operation, the total and the unit labour and machine cost, in your rates' currency.
The calculation runs in your browser; nothing is sent. The material cost per piece comes from the summarized BOM and purchase prices.
4. Allocating components to operations
Component allocation links each BOM line to the routing operation that consumes it. It is what delivers the tubes to the saw and the wheels to assembly, and avoids issuing from stock, at the first operation, parts that will only be needed two days later. Without allocation, most ERP systems assume all components are consumed at the first operation.
- The same part can appear on several lines: the M8 screw is under the frame (8) and under the handle (2). These are two BOM lines, each with its own allocation; here both go to assembly, but they could go to two different operations.
- The BOM structure often follows the routing: a sub-assembly matching an assembly step becomes a level of the manufacturing BOM; a grouping without its own step becomes a phantom item.
- A BOM change can affect the routing: an added component must be allocated to an operation, or it reaches the wrong station. The impact analysis of a change must therefore look at both.
5. In the ERP and PLM
- ERP: the BOM and the routing are two separate objects, attached to the same item. In SAP, for example, routings are created, changed and displayed with transactions CA01, CA02 and CA03, and component allocation is done from the routing. Odoo attaches operations and work centres directly to the BOM, in the Manufacturing app.
- PLM: when manufacturing engineering prepares production in the PLM, the routing is often called a BOP (bill of process), managed with the manufacturing BOM then passed to the ERP. See BOM to ERP integration.
- CAD and PDM: they do not know the routing. They provide the engineering BOM and the drawings that the routing references, operation by operation.
6. Pitfalls
- Times in different units: minutes here, hours there, hundredths of an hour elsewhere. A factor of 60 in a routing distorts capacity and cost without anyone noticing.
- Setup counted per piece: setup time is paid once per batch. Putting it in the run time inflates the cost of large batches and underestimates small ones.
- A phantom without an operation: if a sub-assembly becomes a phantom, its assembly time must move into the parent's routing, or it disappears from capacity planning.
- One routing for several ways of working: when a part can be made on two machines, you need an alternate routing, not an average one.
Printable version: the full example as a PDF (A4, no sign-up): BOM, routing and work order.
7. FAQ
What is the difference between a BOM and a routing?
The bill of materials (BOM) says what the product is made of: components and quantities. The routing says how it is made: the sequence of operations, the work centre of each and its times. The work order brings both together: a list of components to pick and a list of operations to perform.
What is a routing in manufacturing?
The ordered sequence of operations needed to make an item, with for each the work centre (machine or shop), the setup time, the run time and often tooling and instructions. Some ERP systems call it a router.
What is component allocation to operations?
The link between a BOM line and the routing operation that consumes it: tubes at cutting, screws at assembly. It delivers each component to the right station at the right time. Without allocation, the ERP assumes all components are consumed at the first operation.
How do you calculate the time and cost of a work order?
For each operation: time = setup + quantity × run time, cost = time × the work centre's hourly rate. Add up the operations, add the cost of the BOM components, and divide by the quantity for the unit cost. Since setup is paid once per batch, the unit cost drops as the quantity grows.
What is a BOP (bill of process)?
The name PLM systems give the routing when it is managed with the manufacturing BOM, before being passed to the ERP: the BOM says what, the BOP says how and where, with the same links between components and operations.
Bill of materials (BOM) series — the site's twelve articles on the BOM, from the concept to the ERP:
- Bill of materials (BOM): definition, types, roles of PDM, PLM and ERP
- Multi-level, single-level, indented or summarized BOM
- Where-used: find every assembly that uses a part
- Phantom BOM and phantom assembly
- BOM vs routing (this page)
- eBOM vs mBOM: the difference, with an example
- BOM to ERP integration: the 4 architectures
- BOM management software: how to choose
- Free multi-level BOM Excel template
- Part numbering and properties: where a correct BOM starts
- ECR / ECO: controlling BOM changes
- PDM / PLM glossary: eBOM, mBOM, revision, vault…